Construction Delay Claims: Types, What You Must Prove, and the Daily Records That Win Them

A construction delay claim asks for more time, more money, or both, because work was delayed by an event the contractor was not responsible for. To succeed, a claim usually has to prove four things: what happened and when, that it was caused by the other party or an excusable event, that it delayed the critical path or completion date, and how much time and cost it caused. Delays are commonly grouped as excusable (time only, such as unusual weather), compensable (time and money, such as owner changes or late access) and non-excusable (the contractor's own fault). The evidence that decides most claims is same-day records: daily reports with delay start and end times, crews and equipment idled, the responsible party, written notice, and photos with a verified time and location. Daily Site Log records delays this way and produces a project delay PDF, from $0 a month.

Short version

Most delay claims are not lost on the law. They are lost on records. When the owner or GC asks "which days, how long, who was idle, and why?", the party with a complete run of same-day daily reports usually wins.

This guide is general information, not legal advice. Your contract governs; for a large claim, talk to a construction lawyer or claims consultant.

Types of delay

TypeWho is responsibleWhat you can usually recoverExamples
Excusable, non-compensableNobody (neutral event)Time onlyUnusually severe weather, strikes, some force majeure events
CompensableOwner, GC or their agentsTime and moneyLate drawings or approvals, changes, no access, owner-supplied materials late
Non-excusableYouNothing (you may owe liquidated damages)Your crew short, your supplier late, your rework
ConcurrentBoth parties at onceDepends on contract and jurisdictionLate access and your own crew shortage on the same days

How a delay is classed depends on your contract's wording. See construction delays for causes and liquidated damages for what happens on the other side.

The four things every claim must prove

  1. Event: what happened, on which dates, from what time to what time.
  2. Cause and responsibility: who or what caused it, and that it was not your risk under the contract.
  3. Effect on time: that it delayed critical work or the completion date, not just a task with float.
  4. Quantum: how many days, and what it cost: idle labour hours, standing equipment, extended site overheads.

Daily reports carry points 1 and 2 almost entirely, and provide the raw data for 3 and 4.

Delay analysis, in plain words

MethodWhat it doesWhen it fits
As-planned vs as-builtCompares the original schedule to what actually happenedSmall and medium claims with good daily records
Impacted as-plannedAdds the delay events to the original scheduleQuick estimates; criticised for ignoring what actually happened
Time impact analysis (TIA)Inserts each delay into the schedule update current at the timeProspective extension-of-time requests; commonly expected on larger jobs
Windows analysisReviews the schedule month by month (or by window)Long projects with many overlapping delays

Whichever method is used, it is only as good as the record of what happened each day.

The daily records that win claims

For every delay, on the day it happens, record:

  • Type of delay (weather, late material, no access, design information, inspection, other trade, change)
  • Start and end time: "07:30–11:00", not "morning"
  • What stood idle: crew by trade and headcount, equipment by name
  • Impact: labour hours and equipment hours lost
  • Responsible party, in plain words
  • Notice: who you told, how, and when
  • Photos taken in an app that stamps time and GPS, so nobody can argue when they were taken

Then send the report to the GC or owner that day. A dated report in their inbox doubles as written notice in many cases. Follow your contract's notice clause exactly.

Delay entry in a daily report
A delay recorded the same day: type, times, impact and responsible party.

From daily records to a claim pack

  1. Pull every delay for the period from your daily reports.
  2. Group by cause and responsible party.
  3. Total the hours: idle labour by trade, standing equipment, extra supervision.
  4. Line it up against the schedule: which activities moved, and did completion move?
  5. Attach the evidence: the daily reports, photos, notices and correspondence.

Daily Site Log does steps 1 to 3 for you. Every delay is a structured record in a sealed daily report, and one click exports a project delay PDF with dates, times, causes, responsible parties and linked photos. Start free, or read how to document delays from your phone.

Common mistakes

  • Missing the notice deadline. The most common way good claims die.
  • Vague entries: "waiting on drywall" proves almost nothing.
  • Reconstructing records weeks later. Same-day records carry much more weight.
  • Gaps in the record. A complete run of reports, including quiet days, makes the bad days believable.
  • Ignoring your own delays. Concurrent delay arguments are won by honest records, not by leaving things out.

Sources

Frequently asked questions

What is the difference between excusable and compensable delay?

An excusable delay is one the contractor is not responsible for, so it usually earns extra time but not money, for example unusually severe weather where the contract treats it that way. A compensable delay is caused by the owner or its agents, such as late drawings, changes or no site access, and usually earns both time and money. A non-excusable delay is the contractor's own responsibility and earns neither. Your contract's wording decides which applies.

How long do I have to give notice of a delay?

It depends on the contract. Many standard forms require written notice within a short period, often 7 to 21 days of the event or of when you became aware of it, and some say a late notice loses the claim. Check the notice clause in your contract and send written notice the same day where you can.

What is delay analysis?

Delay analysis is how the delay's effect on the completion date is measured. Common methods are as-planned vs as-built comparison, impacted as-planned, time impact analysis (inserting the delay event into the schedule at the time it happened) and windows analysis (reviewing the schedule period by period). Large claims usually use a scheduling expert; small claims often rely on a clear as-planned vs as-built comparison backed by daily records.

Can a subcontractor make a delay claim?

Yes, normally against the party it contracts with, usually the general contractor, under the subcontract's terms. Subcontractors are often hurt most by poor records, because the GC's daily log tells the GC's version. Keep your own daily report and send it to the GC daily.

What records do I need for a delay claim?

Daily reports showing the delay each day it happened (cause, start and end time, crew and equipment idle, responsible party), the baseline and updated schedules, written notices and correspondence, photos with time and location, delivery records, and cost records for idle labour and equipment.