Daily construction report · DCL-2026-4K7Q2
Maple Street Retail Buildout
Friday, 9 May 2026 · 07:00 to 16:30
1 Work performed
Completed slab prep and rebar placement at grid B4. Electrical conduit rough-in on level one: south corridor complete, north corridor 60%. Interior wall framing in the south wing, 14 of 22 bays. Staged framing lumber at the south entrance for tomorrow. East perimeter grading finished, drainage flow confirmed.
- Areas
- Grid B4, level 1, south wing, east perimeter
- Subcontractors
- Volt Electric
- Planned tomorrow
- Pour B4 slab, finish north wing framing
2 Labour
20 workers · 142 hours| Trade | Company | Workers | Hours | Notes |
|---|---|---|---|---|
| Concrete forming | Own crew | 8 | 7.5 | Slab prep at grid B4 |
| Electrical rough-in | Volt Electric | 4 | 6 | Level 1 conduit run |
| Site grading | Own crew | 2 | 5 | East perimeter |
| Framing | Own crew | 6 | 8 | Interior walls, south wing |
3 Equipment
| Equipment | Qty | Hours | Status | Notes |
|---|---|---|---|---|
| Mini excavator | 1 | 5 | Active | East grading |
| Scissor lift | 2 | 6 | Active | Electrical rough-in |
| Concrete mixer | 1 | 0 | Idle | Awaiting rebar |
4 Materials and deliveries
| Item | Supplier | Quantity | Time | Status |
|---|---|---|---|---|
| Framing lumber 2×6×16 | BuildRight Supply | 120 pcs | 08:10 | Received |
| Rebar #4, 20 ft | Metro Steel | 60 sticks | 10:05 | 2 h late |
5 Delays and issues
Rebar arrived 2 hours late. Placement at B4 moved to the afternoon. No effect on tomorrow.
Concrete mixer idle until rebar placement was confirmed.
6 Safety
- Incidents
- None
- Toolbox talk
- Done, 07:05
- PPE checked
- Yes
- Housekeeping
- Walk at 14:30
All workers in hard hat, hi-vis and steel toes at start of shift. South entrance staging area cleared. First aid kit location confirmed with crew leads.
7 Photos
6 · time, GPS and hash on each
2026-05-09 09:12 · 41.878114, -87.629798 (±6 m)
2026-05-09 10:41 · 41.878102, -87.629811 (±5 m)
2026-05-09 12:03 · 41.878131, -87.629760 (±8 m)
2026-05-09 13:27 · 41.878090, -87.629845 (±7 m)
2026-05-09 07:05 · 41.878120, -87.629790 (±9 m)
2026-05-09 10:05 · 41.878160, -87.629700 (±11 m)8 Final notes
GC reviewed progress at 13:00 and approved B4 slab for pour. Framing crew back at 07:00 to finish the north wing. Forecast clear, no delays expected.